When you convert a garage, the part of the job that surprises most London homeowners isn’t the insulation or the window. It’s what sits under the old garage door. The new wall that fills that opening needs something solid to stand on, and on a lot of garages there’s nothing there except the thin edge of the floor slab. Building control will want to know what’s underneath before any bricks go up.
This guide explains why garage conversion foundations matter, how the existing ones are checked, the usual ways of supporting the infill wall, and the London ground conditions that can change the answer.
Why the garage door opening is the weak spot
Garage walls usually sit on a strip foundation, but the doorway was built to let a car in, not to carry a wall. Above the opening there’s a lintel; below it there’s often only the floor slab, and sometimes not even a proper edge to that.
Hertfordshire Building Control puts it plainly in its garage conversion guidance note: very occasionally the house foundation continues under the garage door, but in most cases a new section of foundation is needed because the edge of the garage floor slab is often not adequate to support the load. The Welsh Government’s guidance on infilling a garage door makes the same point: the existing garage foundation is probably a shallow slab, so a new foundation may be needed for the new wall.
A brick or block wall with a window in it is heavy. If it’s built straight off a slab that can’t carry it, the usual result is cracking along the new wall and at the joints with the old brickwork, which is far harder to put right once the room has been plastered and decorated.
How the existing foundation is checked: the trial hole
The check is simple. A small hole is dug next to the slab, in front of where the garage door used to be, to see whether there’s a wall and foundation under the edge and how deep it goes. Rochdale’s building control guide says a trial hole should be excavated next to the slab to verify that the slab is supported on a wall and foundations, and that if a suitable foundation isn’t found, it may be necessary to install one.
We dig the trial hole early, before the design is fixed, because what we find decides the detail for the whole front wall. It’s a short job, and it removes the biggest unknown in most garage conversions. It also tells us about the soil, which matters for the depth of any new footing.
Your building control body has the final say. Whether you use the council or an approved inspector, tell them what the trial hole showed and agree the approach before work starts. Our garage conversion building regulations checklist sets out the other inspections.
The usual ways to support the infill wall
Council guidance varies a little in the detail, but the options are broadly the same everywhere. The right one depends on what the trial hole shows, the wall you’re building and what building control accepts.
1. Build off an existing foundation
If the trial hole finds a suitable foundation running under the opening, East Sussex Building Control Partnership’s garage conversion guidance says you can build off it, provided your building control officer is satisfied. This is the best outcome, but don’t assume it until you’ve seen it.
2. Dig a new foundation
Where there’s no foundation, the most common answer is a new strip of concrete under the opening. The ESBCP guidance describes a new trench-fill foundation dug to at least 1m deep, or the same depth as the existing house foundation if that’s deeper, founded on firm undisturbed ground and inspected by building control before the concrete is poured. Tendring’s guidance says the depth depends on the ground and the existing foundation, and is generally between 750mm and 1,000mm. Depths are set for each site, so treat those figures as a guide rather than a target.
3. Span the opening with lintels or a beam
For a single garage door, a beam can sometimes bridge the gap below floor level, bearing on the brickwork or foundations either side. Tendring gives an example of two concrete lintels with at least 150mm of end bearing cut into the existing brickwork, and Rochdale mentions reinforced concrete lintels installed below slab level as an alternative to a new foundation. ESBCP says this should be agreed with the building control officer on site before it goes in. On wider double openings, or where the side walls themselves are weak, this route needs an engineer’s input.
4. A lightweight infill on a thickened slab
Tendring notes that if the slab was thickened at the door opening and a lightweight infill is proposed, such as a timber-framed wall, it may be possible to build it on the existing floor, once the edge of the slab has been exposed and checked. This can suit a wall that’s mostly window, but the timber frame still needs a damp-proof course, insulation and proper weathering outside.
What affects foundation depth in London
Much of north London sits on clay, and clay is the main reason a “small” garage foundation can end up deeper than people expect.
- Clay soils. The Welsh Government guidance explains that some clay soils shrink and swell as their moisture content changes, mainly in roughly the top 0.75m, so foundations are taken deeper to get below that movement.
- Trees and hedges. Roots draw water out of clay, and a large tree near the front of the house can mean a noticeably deeper footing. Removing a tree can cause problems too, because the ground may swell back. Our guide to building near trees explains how depth is worked out.
- Drains. Load spreads down from a foundation at about 45 degrees. If a drain runs close by, the foundation usually has to go at least as deep as the bottom of the drain trench. Drains often run across driveways, so check before you dig. If there’s an inspection chamber in the way, see our article on a manhole inside an extension.
- The neighbour’s house. On a semi or terrace, the garage may sit next to the neighbour’s wall. Digging close to their foundations, and deeper than them, can bring in the Party Wall Act. Our guide to party wall notices for digging foundations explains the 3m and 6m rules.
Don’t forget the rest of the garage
The door opening is the usual problem, but it isn’t the only one.
- The side and rear walls. Many attached garages have single-skin walls that were never meant to carry more than a light roof. Lining them is fine; adding load to them, such as a new heavy roof, a room above or a steel, needs an engineer to check the foundations as well. Building a room on top is a separate project, covered in our extension over a garage guide.
- New internal walls. A stud partition for a shower room or storage cupboard is light, but a block wall built on the slab is a point load the slab may not be designed for.
- The floor itself. The slab often sits lower than the house floor and may have no damp-proof membrane. Whether you raise it or lower it changes the detail at the front wall too. See garage conversion floor damp and lowering a garage floor.
A sensible order of work
- Check planning first: some estates have a condition keeping the garage for parking.
- Dig the trial hole and look for drains and nearby trees.
- Agree the foundation or lintel detail with building control (and an engineer, if needed).
- Serve any party wall notices in good time.
- Remove the door, excavate, and have the trench or support inspected before concrete goes in.
- Build the infill wall with a damp-proof course linked to the floor’s damp-proof membrane, then insulate and finish. Our guide to infilling the garage door opening covers the window and the look of the new front.
Frequently asked questions
Can I build the new wall straight onto the garage floor?
Only if building control agrees that the slab can take it, which usually means exposing the slab edge and finding it was thickened or sits on a wall. For a brick or block wall, most guidance expects a proper foundation or a lintel spanning onto the existing footings.
How deep does a garage infill foundation need to be?
It depends on the soil, nearby trees, drains and the depth of the existing foundations. Council guidance quotes figures such as 750mm to 1,000mm, or at least 1m, but on clay near trees it can be deeper. Building control confirms the depth on site.
Who decides whether my garage foundations are good enough?
Your building control body, based on what the trial hole shows. Where loads are higher or the ground is difficult, they may ask for a structural engineer’s design.
Does the foundation need inspecting?
Yes. Building control normally wants to see the excavation before the concrete is poured, so plan the dig and the pour close together.
Planning a garage conversion in London?